Mr. Rotimi Amaechi, the Minister of Transportation has said that he was not impressed with the pace of work at the Lagos end of the Lagos-Ibadan rail project.
Amaechi expressed his disappointment during the monthly inspection of the project in Ibadan on Tuesday.
“There is a slow pace of work in the Lagos axis of the project,
“The expectations from the sub-contractor appointed for the relocation of pipes and all, were not met.
“The persons relocating the water pipelines are expected to finish by November 2 but they have come up with different excuses that they discovered other utilities underground.