FG asks Lagos-Ibadan railway contractor to work day, night (Punch)

The Federal Government has advised the contractor handling the 150-kilometre Lagos-Ibadan railway project, China Civil Engineering Construction Corporation, to work day and night to avoid extending its delivery date beyond December this year.

The Minister of Transportation, Rotimi Amaechi, stated this on Monday after the monthly meeting of the Project Steering Committee with the CCECC team at the Papalanto rail/work station in Ogun State.

Although he acknowledged that there had been remarkable progress in the pace of work done in the last one month, he noted the rainy season would pose a major challenge.

“The rain will be a major setback on the plans. The CCECC is the company that has to find the engineering solution to this. But whether they find a solution or not, the element cannot be ignored. That’s why I advised that they should work day and night to achieve the set goals,” the minister stated.

Amaechi also said the contractor would begin the laying of the track on the new line next month, and was optimistic that the December delivery date for the $1.5bn standard gauge rail line was feasible.

According to him, a train station in Abeokuta, Ogun State, had to be moved to the North-West to avoid demolishing about 1,004 buildings in the area.

Amaechi said the biggest challenge of the project at the moment was with the Lagos corridor where many utilities such as power lines, water pipelines and bridges were on the rail’s right of way, thus hindering the construction. Read more

Exit mobile version